07/10/2012

Spray On the Savings with Polyurethane Foam Insulation

How to evaluate SPF’s viability for your roof and ensure a successful installation

By Richard L. Fricklas

 
  • /Portals/1/images/OnlineImages/2012/0712/rn/1-ashrae.jpg

    The law of diminishing returns, as illustrated by ASHRAE here, refers to the point after which costs rise faster than energy is conserved.

  • /Portals/1/images/OnlineImages/2012/0712/rn/2-flashing.jpg

    Use self-flashing to rehabilitate metal edges, curbs, and counter-flashings.

  • /Portals/1/images/OnlineImages/2012/0712/rn/3-hydrovac.jpg

    A clean substrate is essential, so use a high-pressure, low-volume wet-vac to remove loose surfacing and dirt from existing gravel-surfaced built-up roofing.

  • /Portals/1/images/OnlineImages/2012/0712/rn/4-attach.jpg

    Determine the attachment of the old roof. If you find that it’s suspect or consistent, the existing roof system can be mechanically attached before you spray the new SPF system.

  • /Portals/1/images/OnlineImages/2012/0712/rn/5-robot.jpg

    : A wind shield coupled with a robotic SPF applicator minimizes overspray.

Good building management requires sound decisions on a wide spectrum of subjects, not the least of which is the all-important roof – the Fifth Wall.

When the roof’s condition or lack of maintenance become issues, lack of adequate management reveals itself at the most inconvenient times, usually during a major thunderstorm or record blizzard. Not only must you then deal with water damage, but roofing companies will be swamped with similar calls for service and may not be able to get to your building for days or even weeks.

With semi-annual scheduled inspections and an up-to-date roofing file, it is possible to minimize the potential for roofing failure while also updating your estimate of the remaining roof life for replacement budgeting purposes.

Assume we have decided to replace the existing roof system with a sprayed in place polyurethane foam system. That decision process has included cost analysis, warranty information, and future needs for the building.

Roofing experts will then gather information on what is currently keeping the water out. They will first need to know how many roof systems are in place. Most building codes limit the building to two membrane systems, so if there are already two in place, at least one must be removed. (When the number of roofing membranes are counted, it is important to note that building codes do not count coatings as separate membranes.) When re-roofing or re-covering, the building must be upgraded to meet the current roofing code.

Compliance items will include:

  • Scope of wet insulation. No code permits placing a new roof system over wet insulation or a rotted deck. (In some parts of the Southwest, loose-fill volcanic pumice was once an acceptable insulation, but the codes no longer allow it. When this kind of insulation is encountered, regardless of any other condition, the roof over it and the pumice must be removed before a new roof can be installed.)
  • Slope of new system. Some codes now permit “positive drainage,” while others may call for a minimum of 0.25-inch slope (2%) per foot. Tapered insulation ensures good slope to drain. Using crickets and saddles will also help direct the water to a drain or scupper.
  • Amount of thermal insulation. Prior to the oil embargo of 1972-1973, typical roof insulation thickness would have been 0.75 inches with an R value of 2.75 to 3. With all the focus on energy conservation today, minimum R-values are more likely to be 10 times that, around R=30. Even with more efficient thermal insulations, that increase in R-value presents in a substantial increase in the thickness of the roof system, which in turn will require elevating roof edges and curbs at significant cost. At a certain point, costs rise faster than energy is conserved, a principle known as the law of diminishing returns. In addition, published R-values should be based upon long term thermal resistance (LTTR).
  • Eligibility for a new roof warranty. Most membrane manufacturers will require all existing roof systems be removed down to the deck, and that thicker membranes (i.e., at least 90 mil instead of 45 mil) be employed where there will be significant roof traffic or where severe hail might occur.

Top 10 Reasons to Consider Spray Foam

1.    Lightweight at only 2 pounds per cubic foot.

2.    Provides an exemption to the code limit of two existing membranes.

3.    Tenacious adhesion allows it to stick to a variety of substrates, and because SPF is fully adhered, it limits lateral moisture migration.

4.    Self-flashing. Can be used to rehabilitate metal edges, curbs, and counter-flashings.

5.    Can be field-tapered to solve ponding problems.

6.    Punctures in a new system are easily repairable by in-house personnel.

7.    Exhibits excellent lifecycle with recoating typically required every 5-7 years.

8.    Eliminates thermal bridging at joints of insulation board stock and through metallic insulation fasteners.

9.    Makes an ideal and effective air barrier.

10. System can quickly be ready for foot traffic.

What to Consider During an SPF Installation
When installing spray foam insulation, proper surface preparation is vital. For existing gravel-surfaced built-up roofing, use a high-pressure, low-volume wet-vac to remove loose surfacing and dirt. A clean substrate is a must.

Next, determine the attachment of the old roof. If it’s suspect or inconsistent, you can mechanically attach the existing roof system before spraying down the new SPF. Also make sure to stick to the SPF system provider’s instructions for use, including using a primer and choosing a recommended coating, such as acrylic, silicone, or urethane elastomer.

The system also needs adequate compressive strength to resist foot traffic and hail impact – the recommended density is at least 2.75 pounds per cubic foot. A wind shield used with a robotic SPF application will minimize overspray. Most importantly, the roofing contractor must be accredited by the Spray Polyurethane Foam Alliance (SPFA).

Learn More
SPFA offers a wealth of information on proper spray foam application, as does the National Roofing Contractors Association (NRCA), RCI Inc., and the standardization body ASTM. Look into some of these documents to beef up your SPF knowledge:

SPFA: AY-102 Guide to Selection of Coatings, AY-104 SPF Systems for New and Remedial Roofing, AY 107 SPF Blisters, AY-137 Equipment Guidelines, AY 139 Repair of SPF Hail and Wind-driven Damage, SPF Live Cycle Cost Study (Michelsen Technologies)

NRCA: Field and Laboratory Assessment of SPF Roof Systems (4th International Symposium on Roofing Technology -1997), NRCA Manual on SPF Systems, NRCA SPF Roof Systems

ASTM standards: C1029 Specification for SPF Thermal Insulation, D5469 Guide Application of New SPF, D6083 Acrylic Coatings, D6694 Silicone Coatings, D6705 Repair and Recoat, D6947 Liquid-Applied Moisture Cured Polyurethane Coating, D7119 Sampling SPF and Coating, D7425 Standard Specification for SPF Used for Roofing Applications

RCI: Field Performance of SPF Foam Flashings by Rene DuPuis, 2004; Sustainability Characteristics of SPF Roofing and Insulation Systems by Mason Knowles, 2004

Other useful resources: Maintenance and Repair of SPF Roofing by the U.S. Department of the Interior, 1994; sprayfoam.com

 

Richard (Dick) L. Fricklas was technical director emeritus of the Roofing Industry Educational Institute prior to his retirement. He is co-author of The Manual of Low Slope Roofing Systems and continues to participate in seminars for the University of Wisconsin and RCI Inc., the Institute of Roofing, Waterproofing, and Building Envelope Professionals. His honors include the William C. Cullen Award and Walter C. Voss Award from ASTM, the J. A. Piper Award from NRCA, the William C. Correll award from RCI, and the James Q. McCawley Award from the MRCA. Dick holds honorary memberships in both ASTM and RCI Inc.

 

Specifying SPF Roofing Systems
Is a spray polyurethane foam system right for your next roofing project? Find out now.

Quick Fixes for Sprayed Polyurethane Roof Systems
How to deal with damaged SPF insulation.

SPF, Energy, and the Environment
The pros and cons of SPF roof systems.

 


Visit our website today to learn about the design flexibility of a Morton building and the endless possibilities of partnering with our designBUILD team.


Wood construction is both cost and energy efficient. Check out Morton Buildings and our designBUILD team online today to discover all the benefits of post-frame construction.


When choosing a metal-clad building for your next construction project, consider Morton Buildings, Inc., and their designBUILD team, we’ll make your dream a reality.

We Can Help You Reduce Energy by 30%

Our mission is to help our customers manage their buildings' energy costs, improve reliability, and enhance performance while having a positive impact on the environment.
CLICK HERE to find out how.

Add highly responsive multi-zone comfort to any building project, in any climate. Our CITY MULTI H2i R2- and Y-Series VRF systems give you flexibility to fit the needs of any building. Enjoy 100% heating capacity at 0°F outdoor ambient, and 85% heating capacity at -13°F outdoor ambient.  For more information, log on to www.mitsubishipro.com


Visit our website today to learn about the design flexibility of a Morton building and the endless possibilities of partnering with our designBUILD team.


Wood construction is both cost and energy efficient. Check out Morton Buildings and our designBUILD team online today to discover all the benefits of post-frame construction.


When choosing a metal-clad building for your next construction project, consider Morton Buildings, Inc., and their designBUILD team, we’ll make your dream a reality.

We Can Help You Reduce Energy by 30%

Our mission is to help our customers manage their buildings' energy costs, improve reliability, and enhance performance while having a positive impact on the environment.
CLICK HERE to find out how.

Add highly responsive multi-zone comfort to any building project, in any climate. Our CITY MULTI H2i R2- and Y-Series VRF systems give you flexibility to fit the needs of any building. Enjoy 100% heating capacity at 0°F outdoor ambient, and 85% heating capacity at -13°F outdoor ambient.  For more information, log on to www.mitsubishipro.com

 
comments powered by Disqus

Related Products

Lighting
Interiors