Post-Frame Fire Walls: The Economical Alternative?

 
Are Post-Frame Fire Walls the Economical Alternative?

The National Frame Building Association (NFBA) has successfully tested a post-frame 3-hour fire wall system that can now be incorporated into a post-frame building without having to seek out expensive traditional non-wood framing systems.

Full-scale testing of a 3-hour post-frame fire wall in December 2011 by Underwriters Laboratories (UL), Northbrook, IL, showed for the first time that a wood-constructed assembly is a viable alternative to a traditional block wall system.   

The post-frame building system is categorized as a Type 5 structure under the International Building Code (IBC). An hourly rated wall— rated as high as 3 hours—is often required to separate building areas or occupancy types to meet the IBC requirement for life safety.

 For architects, builders, and engineers, that traditionally has meant using a rated 8-inch or 10-inch concrete block wall on a concrete foundation, but with this recent test exceeding hour-rating expectations, that may no longer be the case.

“The post-frame assembly nearly made 4 hours (3 hours and 47 minutes), thus obtaining UL’s 3.5-hour rating,” said Leo F.  Shirek, co-chair of NFBA’s Technical and Research Committee and a member of its 3-Hour Post-Frame Fire Wall Subcommittee. “It’s quite a testament to the quality of post-frame construction.”

The test assembly was a post-frame structure with four layers of 2 x 6 laminations in the columns, spaced 8 feet apart with 2 x 4 girts 16 inches on center applied horizontally on each side. The frame was then sheathed with four staggered layers of 5/8 type X drywall on both sides. All joints were untapped.

Post-frame wall assembly is an extremely economical alternative, Shirek says. “We began testing work for this project in early 2011 knowing that, from an industry standpoint, we could create a wall that was much more cost-effective than a typical block wall, which costs $12−$15 per square foot. We felt that a post-frame fire wall with drywall could potentially halve that cost.”

 Sherik notes that a post-frame fire wall is faster to erect than a stud-wall system, a light-gauge steel-stud wall system, and particularly block walls, which generally require an expensive foundation. “A post-frame wall can be built and incorporated into the natural flow of the building process, possibly saving as much as a couple of weeks in completion time.”

 “We are optimistic that this test will be a building block for other approvals and possibly for other future tests that can benefit the industry,” Shirek says.  Testing, which follows the requirements of the UL 263 (ASTM E119) standard of ASTM International [formerly known as the American Society for Testing and Materials], included a fire test and a stringent water-pressure test.

 


Visit our website today to learn about the design flexibility of a Morton building and the endless possibilities of partnering with our designBUILD team.


Wood construction is both cost and energy efficient. Check out Morton Buildings and our designBUILD team online today to discover all the benefits of post-frame construction.

When choosing a metal-clad building for your next construction project, consider Morton Buildings, Inc., and their designBUILD team, we’ll make your dream a reality. 

We Can Help You Reduce Energy by 30%

Our mission is to help our customers manage their buildings' energy costs, improve reliability, and enhance performance while having a positive impact on the environment.
CLICK HERE to find out how.


Visit our website today to learn about the design flexibility of a Morton building and the endless possibilities of partnering with our designBUILD team.


Wood construction is both cost and energy efficient. Check out Morton Buildings and our designBUILD team online today to discover all the benefits of post-frame construction.

When choosing a metal-clad building for your next construction project, consider Morton Buildings, Inc., and their designBUILD team, we’ll make your dream a reality. 

We Can Help You Reduce Energy by 30%

Our mission is to help our customers manage their buildings' energy costs, improve reliability, and enhance performance while having a positive impact on the environment.
CLICK HERE to find out how.


 
comments powered by Disqus
09/03/2015

Arizona installation will provide 210 MW of renewable energy.

09/02/2015

Standard to create uniformity, common content for rating programs.

09/01/2015

Guidelines to improve safety of waterways.

08/31/2015

Occupant improvements help recruit new talent.

08/28/2015

Temperatures reach highest point since 1880.

08/27/2015

Large improvements drive water conservation on West Coast.

08/26/2015

Data breaches becoming more common.

08/25/2015

Research shows link between extreme weather events and long power disruptions.

08/24/2015

Specifications to improve wall resiliency.

08/21/2015

New resource can help FMs create scope of custodial work.

08/20/2015

Rule created to stem Legionnaires’ disease outbreak.

08/19/2015

Portable devices encourage sedentary workers to exercise while seated.

08/18/2015

PACE program to drive building improvements.

08/17/2015

Survey shows management systems can streamline work order process.

08/14/2015

Tool will help schools improve air quality.

08/13/2015

Proposed ASHRAE rule to improve communication about energy consumption, forecasts.

08/12/2015

Installations rise as electricity costs drop to an all-time low.

08/11/2015

Linear, low-bay/high-bay LEDs spotlighted as best choices for commercial retrofits.

08/10/2015

Wind, solar set for big increases.

08/07/2015

New requirement will cut food waste.

Page 1 of 56
FirstPrevious[1]2345678910NextLast

Sponsored Links