• Dedicated to the Details

    Heath facility's outcome profits from the project team's collaboration and attention to details
    Sept. 28, 2012
    4 min read
    1652316742154 B 1012 Abby Baystate1

    Design and construction details are often devilish, particularly for healthcare projects. But the project team’s continuous dedication to a myriad of them paid off for the Baystate Medical Center and kept a $296 million, 641,000-square-foot clinical facility on time and budget.

    The addition to the medical center in Springfield, MA, houses a new heart and vascular center, 32 cardiovascular critical-care rooms, and 96 private inpatient rooms.

    Planning began during the financial crisis of 2008, which complicated issues from the outset. While Baystate was committed to moving forward, it recognized that managing the costs and the schedule would be especially critical to achieve success, according to Stan Hunter, Baystate project executive. The construction manager, Suffolk Construction, was brought on board during preconstruction to work with the designers on a variety of cost and scheduling issues.

    GRAND PRIZE

    baystate medical center
    New Construction

    Construction Manager:
    Suffolk Construction (submitter)

    Owner: Baystate Health

    Architect: Steffian Bradley Architects

    Structural Engineer: LeMessurier Consultants

    M/E/P Engineer: Vanderweil Engineers

    Close attention to costs created numerous savings. An alternative to the specified exterior brick netted $100,000, and modifications to a prominent concrete retaining wall designed to resemble natural stone saved another $400,000. Electing to purchase a self-enclosure for a backup generator eliminated $500,000 for a building to house the generator and an underground fuel tank.

    Keeping the existing hospital operational at all times posed further challenges. Detailed phasing, sequencing, and logistics plans kept the main entrance open throughout construction, including the rerouting and upgrading of major utilities. The addition’s location some 12 feet away from the existing hospital required attachments in seven locations (five bridges on various levels and two underground tunnels) without disrupting existing clinical areas. To minimize vibration, Suffolk drilled out foundation supports rather than driving piles.

    Green design elements include a four-story lightwell that reduces the need for artificial lighting. A 15,000-square-foot rooftop healing garden has plantings, a fountain, benches, and walking paths. Located on a third-floor rooftop, the garden is visible from upper floors. The addition’s other buildings have white, reflective roofs.

    Managing and Exchanging the Data
    BIM (building information modeling) was used to handle design conflicts and enhance collaboration across the project team. By creating a virtual model early in the process, all heavy duty welding of materials could be done off-site. Laser scanning used in conjunction with the model expedited mechanical work. Josh DiGloria, senior project manager for Suffolk Construction, says the model allowed the use of laser beams to pinpoint the locations for HVAC, plumbing and medical gas hangers, which were installed before concrete was placed for the floors. With the hangers in place, M/E/P subcontractors began mechanical work one month earlier than initially planned.

    The BIM model was also utilized for facility management and operations. According to Baystate’s Hunter, the model contained so much information that it could have easily overwhelmed the purposes of the FM department, so the Suffolk team worked with Baystate for nearly two years to determine the critical data to extract for O&M, including fire/life safety information. The FM model also expedites such routine tasks as repainting; it contains the formula for all of the paint colors used in the hospital.

    At the conclusion of the project, all documents and drawings were turned over in digital format to Baystate, which had previously used hard copy only. The planning for this exchange had started a year earlier, when Suffolk began holding meetings with Baystate to discuss how the latter could best access the information after completion. The project team was already using Suffolk’s web-based tool for construction, which allowed members 24/7 access to documents and edits. Suffolk adapted the tool to Baystate’s needs and conducted several sessions to train the staff on its operation and maintenance. The entire history of the job — consisting of thousands of pages and every report and shop submittal — was made available to Baystate’s staff.

    Voice your opinion!

    To join the conversation, and become an exclusive member of Buildings, create an account today!

    Sponsored Recommendations

    Sign up for our Newsletter
    Get the latest news and updates.

    Latest from Resiliency & Sustainability

    ID 142922418 © Garn Phakathunya | Dreamstime.com
    Supplement traditional grid energy with distributed energy solutions to gain some control over what you pay for energy.
    Electricity prices are rising across the U.S. Here’s why—and the reasons why distributed energy can help flatten those spikes.
    May 21, 2025
    Chang Kim Photography
    An outside view of Arlington Transit's new operation and maintenance facility, a 3-story structure that opened in November 2024.
    ART’s operation and maintenance facility blends smart design, renewable energy, and scalable infrastructure to support Arlington’s carbon-neutral future.
    May 19, 2025

    Sponsored